Davie is a town, and its Building Division keeps its own way of doing things. Plans go in through one system, get reviewed in a second, and inspections are tracked in a third. The town has its own windows and doors checklist, its own addendum form, and a set of roof inspections that have to happen in a set order.
More about our work in town is on our Davie page.
Where the permit goes
The Town of Davie Building Division sits at 8800 SW 36th Street. Since January 12, 2026, every permit starts in the town’s Online Application Submittal system, and ProjectDox then emails an invitation to upload the plans and documents. ProjectDox has its own rules: each document named exactly for what it is, one NOA per file, one drawing sheet per file, and the same file name when you re-upload a corrected page. Before a reviewer looks at anything, the upload goes through a prescreen, and a file that misses the rules comes back as a “prescreen corrections” task.
Inspections live somewhere else again: the town’s eSuite site shows permit status and results, and inspections can be booked there, through the online submittal system, or on the town’s automated phone line. The phone line needs access and inspection codes from the inspection sheet in the permit package, which the town notes are “not located on the permit card.” Requests received before 4:30 p.m. go on the next business day’s schedule, and the approximate time window shows up after 8:00 a.m. on inspection day. If you need to talk to the inspector, the town says to call between 7:30 and 8:15 that morning.
The windows and doors checklist
Davie’s checklist asks for:
- The building permit application.
- An addendum form signed and notarized by both the contractor and the owner.
- A recorded Notice of Commencement once the job value passes the checklist’s threshold, and a whole-house window job does.
- A copy of the property search from the Broward County Property Appraiser.
- A drawing of the house footprint with every opening numbered, plus the length, width and mean roof height.
- The product approvals “obtained from point of purchase,” the BORA 20-01 window and door schedule (the checklist calls it the installation form), and the Broward County wind load chart for a home (sealed charts are for commercial buildings).
The checklist also suggests sending a signed contract as proof of job value, and we do. Plan review for windows is structural.
The addendum carries two notices worth reading. One says the town has an exclusive franchise with a single waste hauler for construction debris, and the permit won’t be issued without that notice signed. The other says a certified copy of the recorded Notice of Commencement must be posted at the house by the first inspection.
Window and door inspections
On our Davie window jobs, the inspections have run in this order: door and window buck, then framing, then the structural final. The framing visit is where mullions get looked at. We photograph the mullion clips and fastener lengths while the clips are still exposed.
For the final, the permit is posted at the house, and we tell you the day ahead so the inspector can get in.
Reroofs in Davie
A Davie reroof package is thick. When we upload one, it includes the owner’s notification for roofing, the HVHZ roofing application, the roof-to-wall and roofing hurricane mitigation forms, a secondary water barrier affidavit, a rooftop equipment affidavit, an asbestos form, the property appraiser printout and an approval for every roofing product.
Davie’s roofing checklist sets the order. The tin cap inspection “must be approved prior to installing any peel & stick.” The peel and stick inspection happens while it goes on or after it’s done, but before any tile. On our jobs the roof in progress and roof final inspections follow. Tile set in adhesive also needs its uplift test on site, and the town wants workers’ comp on file for the roofing work.
Walk-through permits and HOAs
For simple residential jobs, the town runs walk-through permits on Wednesday mornings, with one review per application and two applications per customer.
When there’s an HOA, we get its approval before we file with the town.
What you’ll sign
The notarized addendum, the Notice of Commencement (notarized), and for a reroof the owner’s notification form. The recording, uploads and inspection requests are ours.
Call (786) 654-8273 if you want us to look at your house in Davie.
Official sources
- Town of Davie Building Division, Windows and Doors Checklist
- Town of Davie, Building Division
- Town of Davie, Inspections
- Town of Davie, Roofing Checklist
- Town of Davie, Addendum Form
- Town of Davie, General Information
- Florida Statutes, section 713.13, Notice of Commencement
- Florida Building Code, Existing Building 2023, reroofing section 706