A lot of people who write “Miami” on an envelope don’t live in the City of Miami. We checked: of our own jobs addressed to “Miami,” only a minority sit inside city limits. The rest were spread across Miami Gardens, South Miami, Cutler Bay and a long list of unincorporated communities that the county permits. Our Miami page explains the folio test that settles it (city folios start with 01).
This guide is for homes that really are in the city.
Two systems, one permit
The City of Miami Building Department’s FAQ says building permits are applied for online, and the city uses two linked systems for it. iBuild is where the application lives. ProjectDox is where the plans and documents are uploaded and reviewed. Together the city calls them ePlan.
ProjectDox has rules that trip people up:
- Every file has to follow the city’s Standard Naming Convention.
- Each plan page needs a blank square in the upper right corner (2×2 inches on a letter page, 3×3 on 11×17) for the city’s approval stamp.
- Sealed documents need a digital signature. A wet signature isn’t accepted in ePlan.
- Files belong in the right folder.
Once prescreen passes, the city’s notice says the project is “assigned to all required disciplines.” For a window and door replacement, the city’s 2026 checklist lists only one discipline, Building.
What the window checklist asks for
The City’s 2026 checklist for exterior windows and doors asks for:
- The building permit application, plus a floor plan marking each window and door that’s changing, with room names on it.
- A schedule tying each window or door to its Miami-Dade NOA or Florida (DBPR) approval, with the size and model of each.
- Bedroom egress windows identified, and each window’s sill height measured to the floor and to the ground outside.
- On the approvals, the design pressures, sizes, mullions and glass type marked.
- A cover sheet with the city’s disclosure that the permit authorizes only the window and door work and “does not legalize any portion of the structure.”
The new units have to fit the existing frame or rough opening. Changing an opening turns the job into a remodeling permit.
For City of Miami addresses, our permit team files each permit and follows it through approval.
Roofs
All roofing work in the city needs a permit, and every roofing product needs an NOA or Florida approval. The city’s 2026 flat roof checklist lists inspections for insulation, base application or hot mop, tin cap and a final. When the home’s just value is over the threshold in the code and it predates the modern codes, a roof-to-wall affidavit comes with the reroof.
Inspections
Window jobs get a window and door buck inspection, then a final. Inspections are requested in iBuild, and some permits qualify for a virtual inspection by video call. The city also lets you watch the inspector’s route on inspection day.
The permit card and approved plans have to be at the house.
Call (786) 654-8273 with your address and we’ll tell you which office it belongs to. For roofs, see roofing in Miami.