Pembroke Pines publishes its permit rules in detail, which helps. The short version: the paperwork is strict, and the window inspections follow a one-page procedure.
Our Pembroke Pines page explains the HOA affidavit and the two window visits.
Filing through the Development Hub
The Pembroke Pines Building Department takes applications, corrections and inspection requests through its online portal, the Development Hub. Inspections can also be requested by phone or on the city website. Requests made by 3 p.m. land on the next business day. The department works Monday through Thursday, so the city’s scheduling page says a request after 3 p.m. on a Thursday goes to Tuesday.
A recorded Notice of Commencement has to be uploaded before the first visit can even be booked. The city’s checklist says it must be “recorded, submitted, and displayed prior to scheduling the first inspection,” and suggests sending it in early so it doesn’t hold anything up. We record it as soon as you’ve signed.
What the city checks in the package
Pembroke Pines’ checklist for windows, doors, garage doors, skylights and shutters (revised 02/19/2026) names the 01/08/2026 revision of the Broward County Uniform Building Permit Application, so that’s the edition we use. Each opening needs its row filled in on the county’s retrofit schedule, with design wind pressures for the house. The package also carries the product approvals, a floor plan or layout, the HOA affidavit, and the city’s Window and Door Inspection Procedure with the permit holder’s signature on it. Review is structural.
The city’s application page says to upload everything at once, because the portal locks after submission until that review cycle ends.
When a reviewer sends comments back, the city wants the corrections uploaded through the portal “separated by file category” and asks that they not be bundled into one PDF or emailed.
Two smaller lines from the city’s own documents: its inspection procedure says “Opening replacements are prohibited on Zero lot properties,” so on a zero lot line home we check that wall with the city first. And the checklist notes that a city ordinance (2013-09) controls who may supply a roll-off container, so the dumpster gets ordered the city’s way.
On inspection day
The inspection procedure puts tools on the permit holder: ladders and anything else the inspector needs. If an inspector allows photos after the structural visit, they have to be printed and labeled by opening number to match the retrofit schedule. Our window jobs there go window attachment, exterior door attachment, then final.
Roof permits
The city’s reroof checklist adds an asbestos release form, the HVHZ roofing package with the owner’s notification, and a roof-to-wall affidavit when the house is insured or valued above the code’s threshold. On our Pembroke Pines reroofs, the inspection list has included underlayment in progress, the tile, shingle or standing seam layer in progress, fire barrier where the system calls for it, daily in-progress visits on built-up flat roofs, and a final roof inspection. Some tin cap inspections came back marked not required.
The final roof inspection is where the uplift test report is collected, and the city wants the original. One of our passing finals carries the inspector’s note that the report “was received in original with raised seal.”
HOA and city review
Our permit team files your Pembroke Pines permit and follows it through approval.
When there’s an association, HOA review comes before the city’s, and we handle that application too.
Signing online
The Broward application has a notarized signature line for the owner or an agent, and the Notice of Commencement is signed by the owner before a notary. If you use a remote notary, check that the notary is registered for online notarizations in Florida.
Questions about your own house? Call (786) 654-8273. For the work itself, see our pages on impact windows and new roofs.
Official sources
- City of Pembroke Pines, Windows, Doors, Garage Doors, Skylights and Shutters Permit Checklist
- City of Pembroke Pines, Window and Door Inspection Procedure
- City of Pembroke Pines, Inspection Scheduling
- City of Pembroke Pines, Information and Forms
- City of Pembroke Pines, Re-Roof Permit Checklist
- Broward County Board of Rules and Appeals, Uniform Retrofit Window & Door Schedule (Policy 20-01)
- Florida Statutes, section 713.13, Notice of Commencement