Pompano Beach does something we don’t see in most cities: the Notice of Commencement gets its own line on the inspection schedule. On one of our door permits there, the first inspection booked was literally called “NOTICE OF COMMENCEMENT.” The recorded notice has to be in place, and inspected, before the work itself is.
That’s one of several Pompano habits worth knowing. Our Pompano Beach page lists the roof inspections and the attachment affidavit.
First, is it Pompano Beach?
A Pompano Beach mailing address covers more ground than the city does. When we mapped our own “Pompano Beach” jobs, a good share sat in Margate, in Coconut Creek, or in unincorporated Broward County, where the county handles permits rather than any city. So the parcel lookup comes first.
The ePlan project and the printed set
Pompano Beach’s Building Inspections Division uses two separate systems: Click2Gov creates the application number, and an ePlan (ProjectDox) account holds the plans. The city notes they “do not share login credentials.” Once a permit is approved, the city expects the approved permit set to be downloaded and printed for the inspector. Every inspection notice we get repeats it: “Please make sure to log in to your ePlan Project to download and print your Approved Permit Set for inspection.”
Inspections can be requested online any day of the week, and Pompano inspects Monday through Thursday; a request in by midnight gets the next available inspection day. The same notices point to a tool called Where Is My Inspector, which posts an estimated arrival time by 8:00 a.m. on inspection day.
Window and door permits
Pompano’s window and door checklist accepts a floor plan or a clear sketch, either a state approval or a county NOA for every product, with the product circled, and the county’s wind load chart for buildings 30 feet or lower. The city lists two building inspections for windows and doors, an attachment visit and a final structural, with a fire department final added where it applies.
Reroofs
Reroofs are their own permit type in Pompano Beach, with tile and low slope roofs sometimes on one permit. It starts with the tin tag, then the mop-in visit, then a check of the tile or shingles while they go on, and it ends with the final structural. On a Pompano roof each inspection is requested in order, before the next layer goes on.
Association approval and the Certificate of Completion
Pompano wants a letter from the association approving the work, and its checklist points out that under Florida Statutes 720.3035 an association can’t require the building permit to be issued before it does its own review.
After the final passes, the city notes that a Certificate of Completion is available on request. We can request it for your records.
What we need from you
Your signatures: on the application papers, and on the Notice of Commencement in front of a notary. Since the notice is the first thing Pompano inspects, signing it early keeps the job on schedule.
Pompano questions go to (786) 654-8273, any time of day. Door options are on our impact doors page.
Official sources
- City of Pompano Beach, Building Inspections Division
- City of Pompano Beach, Submittal Checklists (Window & Door Changeouts, Reroof)
- City of Pompano Beach, Apply for a New Permit
- City of Pompano Beach, Inspection Scheduling and Tracking
- Florida Statutes, section 720.3035, association review
- Florida Statutes, section 713.135, permit applications and the Notice of Commencement
- Broward County, Uniform Retrofit Window & Door Schedule (BORA Policy 20-01)