Not by itself. On a wind mitigation report, “toe nails” describes how the roof framing is attached to the walls, and a new roof covering doesn’t change that unless connectors are added. It’s an easy thing to mix up, because the same form also asks how the roof deck is nailed down.
Toe nails aren’t roofing nails
On Florida’s uniform wind mitigation form (OIR-B1-1802), “toe nails” is an answer to the roof-to-wall attachment question. It describes how the bottom of each roof truss or rafter is fastened to the top of the wall. Toe nailing means nails driven at an angle through the truss into the wall’s top plate, with no metal connector.
The nails that hold down shingles, tile underlayment or metal panels are a different thing. So are the nails that hold the plywood deck to the trusses, which the form asks about separately under roof deck attachment.
That’s why a brand-new roof can still come back “toe nails.” Replacing the roof covering and re-nailing the deck doesn’t change how the trusses meet the walls.
The categories on the form
The current form asks for the weakest roof-to-wall connection on the house, ignoring hip and valley jacks within five feet of a corner. The main answers are:
- Toe nails: angled nails only, or metal connectors that weren’t installed the way they’re supposed to be.
- Clips: metal connectors that don’t wrap over the top of the truss.
- Single wraps: one strap that wraps over the truss, nailed on both sides.
- Double wraps: two straps, one on each side of the truss, each wrapping over it.
- Structural: anchor bolts structurally connected, or a reinforced concrete roof.
The form also sets minimums for counting a connector at all, including at least three nails into the truss. Insurers generally give more credit as you move from toe nails toward double wraps, but how much is up to your insurer and policy.
When a reroof changes the answer
A roof replacement is the easiest time to add connectors, because the edge of the roof is open and the tops of the walls can be reached from above.
Florida law also requires it on some houses. Under section 553.844, a roof replacement on an older site-built single-family home in the wind-borne debris region, built before the Florida Building Code and above the insured-value threshold the statute sets, must include roof-to-wall connection improvements, capped at 15 percent of the cost of the roof replacement. If your home is one of them, it goes into the reroof scope, and we tell you before you sign.
If you want wraps instead of toe nails
Adding connectors to every truss is its own job, and the My Safe Florida Home program lists it as an eligible improvement when its inspector recommends it. The program’s homeowner guide stresses that the upgrade has to be done at every truss or rafter to earn wind mitigation credit, and it describes three ways in: opening the bottom edge of the roof deck, removing soffits, or working from the attic.
What to do with your report
- Read the roof-to-wall box and the photo the inspector attached for it.
- If you’ve had connectors added, get a new inspection; the form is good for up to five years only if nothing changed.
- Keep your reroof permit and deck nailing details with it. Those answer different questions on the same form.
See how we build a hurricane roof, or read about roof replacement. Questions about your report? Call (786) 654-8273.