What a Roof Tear-Off Includes, Step by Step

Old underlayment being stripped during a tile roof tear-off

A full tear-off means every layer of the old roof comes off down to the wood deck, the deck gets repaired and fastened, a new water barrier goes down, then new metal and the new roof covering. In Florida each of those steps has code behind it, and on older houses the reroof is also when the deck gets brought up to the code’s wind retrofit rules. Here’s the order on our jobs and what’s being checked along the way.

1. Paperwork before anyone climbs a ladder

The permit comes first, with the product approvals for the roof system attached. In Miami-Dade and Broward, a reroof permit also carries the “Owner’s Notification for Roofing Considerations.” The roofer has to explain each item on it, and you initial each one. Miami-Dade’s version covers, among other items, deck re-nailing, exposed ceilings, ponding water, overflow scuppers, keeping attic ventilation at least where it was, and a separate permit for reinstalling any solar panels.

2. Setting up the house

Our roof contracts record details the crew needs before day one: dumpster access, a pool or pool enclosure, skylights, gas vents on the roof, and whether any ceiling has exposed wood decking. Gas vents get their own line on the contract for inspection or replacement.

3. Tear-off to the deck

Tile or shingle, old underlayment and old flashing all come off. Our scope says it plainly: the crew keeps going until bare plywood or board decking shows. The code backs this up. New roofing can’t be laid over existing tile, over two existing layers, or over a roof that’s water soaked or deteriorated, and in Miami-Dade and Broward tile can’t go over any existing roof.

4. Deck repair

With the deck bare, soft or rotted sheathing is cut out and replaced. In the High-Velocity Hurricane Zone (HVHZ), the Florida Building Code, Building says plainly that a new roof can’t go on sheathing that’s water soaked or deteriorated to the point it can’t hold fasteners. Damaged fascia is replaced at this stage too.

5. Re-nailing the deck

This is the step that changes how an older roof handles wind. IBHS, the insurance-industry research group behind the FORTIFIED Roof program, says that moving from smooth nails to 8d ring-shank nails at closer spacing can double a deck’s resistance to uplift. For houses that weren’t originally permitted under the Florida Building Code, the Florida Building Code, Residential requires the deck fastening to be brought up when the roof is replaced:

  • Plywood held with staples or small 6d nails gets added ring shank nails, no more than 6 inches apart.
  • Plywood with 8d nails spaced wider than 6 inches gets added nails to close the spacing to 6 inches.
  • Board decking needs at least two 8d nails into each rafter or truss it crosses.

The added nails have to be ring shank nails of a specified size and ring pattern. In Miami-Dade, the roofing company’s qualifier signs a notarized affidavit that the deck attachment and the secondary water barrier meet these sections. On our contracts, the entire deck gets new ring shank nails at 6-inch spacing, whatever the age of the house.

6. Dry-in and the secondary water barrier

“Dry-in” is the code’s term for putting down the first layer of underlayment. For shingle and metal roofs, the residential code accepts three ways to build a secondary water barrier:

  • A self-adhering membrane over the entire deck.
  • Strips of self-adhering membrane at least 3 3/4 inches wide over every plywood joint, with underlayment over the whole roof.
  • Two layers of approved underlayment, lapped and nailed in a set pattern with capped nails.

Tile roofs follow the tile installation manual the code references, and the reroof rules accept a properly installed tile system in place of a separate water barrier. In the HVHZ, nailed underlayment goes down with ring shank nails through metal tin caps in a 12-inch grid, tighter at the laps. That layer is what the first roofing inspection, often called the tin cap or dry-in inspection, looks at.

7. New metal

Old flashing doesn’t go back on if it’s rusted or damaged. On our jobs, the metal is new: drip edge at the eaves and rakes, valley metal, lead boots at the plumbing pipes and new metal vents.

8. The roof covering, and the inspections around it

Shingles, metal or tile go on according to the product approval. The HVHZ code lists inspection points by phase: during or after the underlayment, during installation of the roof covering, and a final once the work is done. Mortar-set and foam-set tile roofs also get a static uplift test before the final.

9. Final, cleanup and paperwork

After the final inspection passes, the permit closes. The debris is hauled away, and the warranty paperwork follows once the job is complete. Keep the permit number and product approvals with it. The wind mitigation form asks about deck attachment and secondary water resistance, and the permit file shows when the work was done.

Want to see how this looks on a real job? Our roof replacement page walks through it with photos, and our hurricane roofing page covers the storm details. Call (786) 654-8273.

See your home with impact windows

Pick a window style, a frame color and a front door, and see them on a South Florida home.

Design your whole home
Written by the Guardian teamGuardian Impact Windows & Roofing, Deerfield Beach, FL · Certified General Contractor CGC1524314 · Certified Roofing Contractor CCC1334906

Promotional Rates End 12-01-2026

Limited time offer, 0% interest

Promotional Rates End 12-01-2026

Limited time offer, 0% interest

Keep reading

More guides for your home